Fundamentals of Construction Contracts: Notice Requirements

» Articles » Construction Articles » Article

November 13, 2013


Contracts almost universally require Contractors to give written notice of change orders and claims. This notice must usually be provided within a specific number of days from the event, which causes the change. Failure to satisfy notice requirements may invalidate your claim, or create a dispute which will consume time and effort to resolve. It is far better to give written notice and eliminate this potential stumbling block.

Contracts require written notice for good reasons. These include the following:

  1. The Owner needs the opportunity to investigate, consider options and make decisions.
  2. The Owner wants the opportunity to keep track of costs.

Exceptions to strict notice requirements have been recognized in some jurisdictions and may include the following:

  1. Constructive Notice – the Owner knew or should have known. This may include verbal notice, discussion at a meeting or superior knowledge by an Owner.
  2. The Owner was not prejudiced by lack of notice. The Owner would not have, or could not have, acted differently, even if it had been given formal written notice.
  3. Defective Specifications. When contracting with the Federal Government,
  4. Contractors are generally compensated for increased costs, reasonably incurred in attempting to comply with defective specifications, regardless of notice.
  5. Waiver of notice requirements. This may occur if the Owner does not enforce the written notice requirements of the contract. The parties, by their actions, may adopt a more informal change order process based upon verbal notice, followed by the incorporation of such changes into formal change order documents.

Regardless of the above exceptions, strict notice is enforced in some jurisdictions.

Continue reading below

FREE Construction Training from Lorman

Lorman has over 37 years of professional training experience.
Join us for a special white paper and level up your Construction knowledge!

Best Practices for Measuring and Documenting Construction Delays

Learn More

Without written notice, your claim may be dead. On large complex projects, it is wise to make a detailed review of the specifications, and compile a table of notice requirements and time limits for giving notice for each requirement.

For more information on notice requirements for construction contracts, visit us at www.lorman.com for all of your contiuing education needs.


The material appearing in this web site is for informational purposes only and is not legal advice. Transmission of this information is not intended to create, and receipt does not constitute, an attorney-client relationship. The information provided herein is intended only as general information which may or may not reflect the most current developments. Although these materials may be prepared by professionals, they should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.

The opinions or viewpoints expressed herein do not necessarily reflect those of Lorman Education Services. All materials and content were prepared by persons and/or entities other than Lorman Education Services, and said other persons and/or entities are solely responsible for their content.

Any links to other web sites are not intended to be referrals or endorsements of these sites. The links provided are maintained by the respective organizations, and they are solely responsible for the content of their own sites.