From Green to Seeing Red

» Articles » Construction Articles » Article

April 23, 2010


There seem to be four stages (so far) of the green building movement in the U.S. First there was Green for Green’s sake: the altruistic goal of environmental improvement. Then there was Green for Greenbacks: when it became stylish to be green and there was a market premium in selling green. After that there was Green for Red Tape: the legislative initiatives, often poorly thought out mandatory greenness. And most recently, Green seeing Red: when the liability costs associated with "failed" green efforts diminish or overwhelm the altruistic, economic or administrative reasons for going green. Not surprisingly all of these stages exist simultaneously, but recent legislative, administrative and judicial developments indicate that this last stage is growing and likely to play a more prominent role in the future. How are parties engaged in construction to best protect themselves as they advance into the green experience?

OWNER: Follow three rules to achieve your goal:

a) Hire competent professionals with appropriate and local knowledge to design and build the project;

b) Use contracts that fairly allocate risk to the owner, designer and builder; and

c) Monitor the work and be ready to modify your goals depending on events.

Continue reading below

FREE Construction Training from Lorman

Lorman has over 37 years of professional training experience.
Join us for a special white paper and level up your Construction knowledge!

Best Practices for Measuring and Documenting Construction Delays

Learn More

Competent LEED Accredited Professionals or others of comparable education and experience who have previously done the type of work required are the starting point. They need experience in green design as well as in the implementation of local administrative and legislative systems.

With the advent of more municipal green requirements, local knowledge is more than just building code experience—it is familiarity with the regulatory system and with local building practices.

Relations with local regulators are essential as many of these regulatory systems are poorly thought out, ambiguous and vague. Further, using builders that have built green projects before not only provides an advantage when calculating LEED credits, but also assures smoother and less expensive implementation during construction and more importantly, during commissioning of the building systems.

Contracts that unfairly allocate risk have always generated unnecessary and costly disputes. The same is true of contracts that mandate unreasonable design or construction performance. For example, many owners seek to shift the entire burden of risk for green building certification to the design professional, general contractor or both. While superficially appealing to party shedding the risk, this approach is simplistic and the wise owner will recognize that it violates one of the cardinal tenets of risk management: risk should be borne by the parties best equipped to bear it and to control the outcome of the endeavor. Certification of a green building is not completely within the control of any single member of the project team and optimal risk allocation strategies will reflect this.

Risk allocation surety products associated with the design and construction team, at least at their present state of evolution, are generally poorly designed to minimize the owner’s exposure. For instance, the highly tradition-bound surety industry typically concentrates on the "Cs" of bonding: capital, capacity, character. "Green" does not start with a "C" and sureties are just now becoming more aware of the concomitant risks. If a surety needs to hire a replacement general contractor and complete a project, how likely is it the owner's green objectives will be fulfilled? Turning now to the design team, the professional liability policy affords the designer—and by extension the owner—no protection if the designer fails to deliver on a promised LEED rating (a promise any insured would be ill-advised to make).

Owners inevitably retain much of the risk of green building. A promising development is the recent evolution of owner-controlled or wrap policies toward more comprehensive coverage of risks associated sustainable development.

Owners have an ongoing responsibility to monitor the design and construction of their green building. While competent designers are essential, the owner has many prompt and considered decisions to make as the design is developed including site planning priorities, material choice and mechanical systems. Only the owner can decide on the trade-offs between fenestration design and mechanical requirements, and their green building implications. As construction proceeds, the owner has a continuing responsibility to oversee the builder's compliance with the contract documents and local regulations. Yet this responsibility cannot be myopic. If unanticipated conditions arise during construction affecting the green calculation, the owner must be willing to consider all alternative mitigation measures. Again, specialists can be of considerable help to the owner. For example, a number of green building experts focus on the technical feasibility and financial returns from tradeoffs between sustainable elements. On larger projects owners have had success utilizing experienced claims analysts to analyze construction schedules and potential claims on a real-time basis, with an eye toward prevention of blunders associated with long-lead "green" items, schedule issues for complex or unfamiliar systems, and a host of other pitfalls.

DESIGNER: Design firms have been in the forefront of the green movement since the 1970s and many have significant green-design capabilities. However, they too have a short checklist to assure they meet all their potentially conflicting requirements:

a) Don’t oversell your capabilities;

b) Develop your contract documents completely; and

c) Provide ongoing design services to assure the green goals are met.

Designers' failures to meet the Owner’s expectations are the major cause of poor and litigious relations. Designers often oversell their capabilities or allow their scope of contracted work to fail to match the promise of the job interview. If the designer knows that the regulatory approval process for a green design sign-off takes 120 days, it is unethical to pretend to the Owner that it can be accomplished in 60 days. If the designer needs local expertise to navigate the local regulatory process, then it must retain the needed skills or clearly advise the client of this skill-set deficiency.

Incomplete design documents are one of the largest causes of construction disputes. It seems likely therefore that as the tide (or tidal wave?) of disputes involving green issues moves forward, incompleteness of design is likely to still be a major cause. Already we can predict that the performance of mechanical systems and the commissioning of that equipment will be major causes of green disputes. Green design requires more design effort and greater diligence in assuring completeness and operational efficiency. Like the admonition to the Owner, the designer starts with the scope of work and contract for those design services. The Designer should not assume that old contracts will serve expanded responsibilities.

It is important to note the relentless commoditization of design services and the corresponding downward pressure on design fees over the last thirty years. This trend has occurred, ironically, during a period where buildings have become increasingly complex, and the added responsibilities associated with green design exacerbate the challenge to the design professional. It is therefore more difficult than ever to produce a correct and complete set of design documents profitably. There is no solution on the horizon to this conundrum. It will call for near-ruthless efficiency on the part of design teams, militating in favor of increasing niche specialization or consolidation into super-sized firms.

Incomplete design is almost always capable of being remedied by more design work.

While the earlier design activities are performed, the more efficient and cheaper it is, there is always a component of the designer’s scope that occurs during construction. During construction the Owner needs the Designer to monitor the green component of the design and keep abreast generally with the construction. Some owners (again of the pound foolish variety) seek to minimize or eliminate the designer’s scope of construction administration services. We would advise design professionals to walk away from any contract that does not include an adequate provision for such services.

The Designer may have to adjust its design to meet the actual conditions encountered in the field. This will require flexibility and ongoing evaluative capabilities. For example, suppose the availability of some local services disappear during the late design or construction stage, therefore eliminating some of the points needed for the desired green certification facility. The designer needs to be prepared to modify some of the design to recoup those points. As a corollary, the Owner needs to be willing to change its objectives and potentially increase both its design and construction budget to meet the changed needs.

BUILDER: Within the last year, the price uncertainty associated with building green has diminished as those attitudes and elements needed to perform green construction have become better understood. This decrease in possible risk to the builder still leaves substantial concerns that should be considered:

a) Does the contract describe the additional level of work and diligence needed and does it properly allocate design issues to the designer?;

b) Does the Builder have the skill set and experience to perform the required green-related work?;

c) Does it have the needed supervisory capability of overseeing the needed subcontractor and laborers to assure continued compliance with the contracts?; and

d) Does the local community have the capability to supply and absorb the differentiated materials associated with the project?

Builder risk associated with green design has increased within the past year. Builders better understand the activity and quality control mandates associated with building green, and green materials are more commonly available, resulting in more stable and known costs. At the same time, the potential risk associated with project failure to meet green design objectives has increased. It is therefore imperative that the construction contract only allocate performance requirements to the contract which he can control or insure. For example, a builder should be extremely cautious about specifications that identify detailed material and equipment items and at the same time also mandate system performance.

Just as the Designer had to be cautious about overselling its green design capabilities, the builder must not represent it has skills it does not have. For example, most green buildings will have a substantial commissioning requirement for the mechanical systems. Where an independent commissioning agent is not called for in the contract documents, the builder must not only have the technical capability available on its construction team, but must know to allocate sufficient time for that work.

Further, having the necessary competent subcontractor set is necessary but insufficient. The Builder must also have in-house management capability to oversee the integration of that builder’s green work into the entire project. That management capability must extend to the documentation of the green related activities and the ability to assure continued regulatory compliance. To the extent outside expertise is needed but not retained by the Owner as described above, it will have to be retained by the Builder.

Amazingly, some communities still seem to have no mandatory recycling procedures. In such a community, it would be difficult for a builder to properly dispose of its segregated materials that comprise the green points available for contractor activity. Therefore it is essential that either the local community has the absorptive capability or that there be nearby vendors or communities that can assist in the recycle process.

There will be claims associated with attempts to comply with green requirements and the failure to comply. How much and many? Lawsuits have been few and far between so far but that will change. As the inventory of certified green buildings continues to swell, litigation will be a lagging indicator of this. The new and additional uncertainty of responsibility guarantees that those associated will need to consider the general outlines described above if they wish to minimize potential disputes in this area. We have hope that the green movement will proceed with minimal claims disruption, but are preparing for the worst. In that regard the observations provided in the paragraphs above have some common elements:

1) Have reasonable and fair allocation of risk—contracts that place all elements of Green compliance risk on any one party are neither fair nor reasonable;

2) Overselling capability or competence leads to a mismatch between technical scope and technical competence, leading to probable claims; and

3) Remain flexible—the purpose of ongoing management is to assure proper performance and adapt to changed circumstances.

ABOUT THE AUTHORS

John Livengood, ESQ, AIA is Associate Vice President for ARCADIS. He is a registered architect with more than 34 years of experience in architectural design, project management, design analysis, and document preparation. He is also an attorney experienced in construction litigation, government contracts, claims analysis, international contracts and arbitration, and a variety of projects that include office buildings, sports stadiums, warehouses, educational institutions, hospitals, wastewater treatment plants, industrial facilities, correctional facilities, roadways, military bases, airfields and air terminals, rapid rail facilities, railroad stations, high-power lines, bridges, microwave communication facilities and powerplants, as well as small residential projects, garden apartment buildings, and high-rise apartment buildings. As an expert witness, Mr. Livengood has testified in court proceedings before boards of contract appeals and in arbitrations on scheduling issues, damages and causation issues. Mr. Livengood can be reached at [email protected].

William Broz, P.E., LEED AP is Operations Manager for the Construction Claims Services Practice in California. He is a registered mechanical engineer and a LEED AP with over 30 years of design, construction and claims experience. He has been a principal in his own design firm and has provided expert services for a variety of project types including educational, commercial, correctional, industrial, and hospitality. His experience includes forensic investigations, expert testimony, deposition, and trial. Mr. Broz can be reached at [email protected].


The material appearing in this web site is for informational purposes only and is not legal advice. Transmission of this information is not intended to create, and receipt does not constitute, an attorney-client relationship. The information provided herein is intended only as general information which may or may not reflect the most current developments. Although these materials may be prepared by professionals, they should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.

The opinions or viewpoints expressed herein do not necessarily reflect those of Lorman Education Services. All materials and content were prepared by persons and/or entities other than Lorman Education Services, and said other persons and/or entities are solely responsible for their content.

Any links to other web sites are not intended to be referrals or endorsements of these sites. The links provided are maintained by the respective organizations, and they are solely responsible for the content of their own sites.